Installation guide

Installation guide

Install your sandwich-panel roof, step by step

Measure, check the roof frame, cut, install, finish. Each step comes with calculators to prepare your order, and a glossary for every technical word.

10 %minimum pitch (≈ 5.7°)
2 mmaximum purlin spacing
1 meffective width per panel
2 to 4fixing screws per m²

Before ordering: check the pitch and measure

Our panels can be installed from a 10% pitch, with no end overlap along the length. Check your , then measure the width and the of each roof slope.

Pitch calculatorHeight and length on the ground are enough

30 %
pitch, i.e. 16.7°
5.22 mslope length (actual length along the slope, without overhang)

Formula: pitch (%) = height ÷ horizontal length × 100.

Panel and accessory calculatorIndicative quantities, to be confirmed by the quote

Range
Roof shape
8panels to order
5.60 mlength of each panel
44.8 m²panel surface area
515 kgestimated weight to unload
90 to 180fixing screws
1 packstitching screws (100 screws)
8eaves closures (1 per panel)
11.2 lmU-shaped verge trims on the gables, + 10 to 15 cm per joint
8 lmridge cap

Available lengths: from 2.10 m to 12.25 m in 35 cm steps; from 12.60 m to 15.75 m as a special length (suitable transport required).

Get the exact price
  1. The width along the gutter, from one gable to the other. One panel covers 1 m of effective width.
  2. The slope length, from the ridge to the gutter edge, following the slope. It is longer than the measurement on the ground.
  3. The overhang: add 20 to 40 cm at the eaves to keep water away from the walls.
  4. The panel length = slope length + overhang, rounded up to the next available length.

Check the roof frame

The panels are laid on made of timber or steel. The greater the , the lower the permissible load: in areas with heavy snow or strong wind, bring the purlins closer together. If in doubt about your roof frame, have it checked by a professional.

Load capacity by purlin spacingPermissible load in kg/m²

Range
185 kg/m²
permissible load (snow, wind, maintenance)

Delivery and storage

Delivery arrives on a 35-tonne curtain-sider, with the panels stacked on pallets. Prepare access and unloading before the day.

Access for a 35-tonne lorry

The address must allow an articulated lorry through. Otherwise, give us another unloading location.

Unloading is your responsibility

Plan for a forklift or a telehandler (Manitou). The calculator above estimates the weight to unload.

Store flat, raised off the ground

Somewhere dry, slightly tilted so that water runs off.

Handle with two people

By the edge, with two people for long lengths, without sliding the panels over each other.

Remove the protective film no later than 30 days after exposure to the sun

After that, it sticks to the panel. Ideally, remove it right after installation.

Cut without damaging the lacquer

Hot cutting burns the lacquer and makes the steel rust. The right tool makes all the difference.

Cut cold

  • Electric shears
  • Fine-toothed metal saw

Never use an abrasive tool

  • Angle grinder, cut-off saw
  • Their hot sparks attack the lacquer
  • They cause rust over the whole surface
  1. Mark the cut with a grease pencil and support the panel on trestles.
  2. Cut slowly, wearing goggles, gloves and ear protection.
  3. Remove the swarf straight away with a soft cloth or brush: it rusts and stains.
  4. Treat cut edges and verges with an anti-corrosion product.

Installing the panels

Tick each step as the work progresses: your progress is saved on this device.

3D installation, step by step

Roof frame, screwing, interlocking, accessories: follow the assembly as on site.
0/8

steps done

Installing the accessories

Tap a point on the house to see what each part is for and how to fix it.

Ridge cap

It covers the top of the roof. Three models depending on the shape:

  • Ridge cap: two-slope roof, fitted astride the top.
  • Wall abutment ridge: single-slope roof against a wall.
  • Closure ridge: single-slope roof with a free top edge.
Screw it to the top of the wave with watertight self-drilling screws. Place profiled foam between the ridge cap and the panels.

Finishing and maintenance

A few minutes on installation day, then a quick check once a year.

On installation day

  • Remove the film and clean off all swarf.
  • Touch up scratches with the touch-up paint in the panel colour.

Every year

  • Visual check: screws, verge trims, ridge, cleanliness.
  • Marine, corrosive or chemically aggressive environment: the standard polyester coating is not suitable, contact us before ordering.

General technical data sheet — Romane Canal, Flat Tile, Trapezoidal Steel

3-page PDF (in French): composition, performance, permissible loads, installation, accessories and delivery. The declaration of performance is sent on request at +33 6 76 45 67 57.

Download

Roofing glossary

The technical words used in the guide and on the website, explained simply.

Sandwich panel
Panel made of two steel sheets and an insulating polyurethane foam core. In a single installation, it replaces the roofing, the insulation and the ceiling.
40/80, 60/105, 50/77 mm
Insulation thickness of a wave-profile panel. The first figure is the thickness in the trough of the wave, the second at the highest point. Example: 40/80 = 40 mm in the trough, 80 mm at the crest.
Effective width
Width actually covered by a panel once interlocked with its neighbour: 1 m for our tile panels.
Polyurethane (PUR)
Insulating foam forming the core of the sandwich panel, between the two steel sheets.
Protective film
Plastic film that protects the lacquered face during transport. Remove after installation, no later than 30 days after exposure to the sun.
Slope length
Length of the roof measured along the slope, from the ridge to the gutter.
Pitch
Slope of the roof, expressed in % (height ÷ horizontal length × 100) or in degrees. Minimum for our panels: 10%.
Overhang
Part of the panel that projects beyond the wall, at the eaves (20 to 40 cm) or at the sides. It keeps rainwater away from the walls.
Gable
Wall whose top follows the triangular shape of the roof.
Purlin
Horizontal member of the roof frame (timber or steel) on which the panels rest and are screwed.
Purlin spacing
Distance between the centres of two purlins. Recommended maximum: 2 m.
Load capacity
Load (snow, wind, maintenance) the panel can bear, in kg/m², depending on purlin spacing.
Ridge, ridge cap
The ridge is the line at the top of the roof. The ridge cap is the metal part that covers it.
Verge trim (U, L)
Profile that finishes the sides of the roof (gables). The U-shaped trim is used when the panel overhangs the wall, the L-shaped trim when it stops flush with the wall.
Eaves closure
Part fixed at the end of each panel, at the eaves. It fills the gap under the wave and hides the insulating foam, against wind, rain and birds. Also called a front cover: it is the same part.
Fixing screw
Watertight screw with washer that fixes the panel to the purlins: 2 to 3 per panel per support, i.e. 2 to 4 per m² on average.
Stitching screw
Small screw that joins two neighbouring panels at their side lap. Allow 1 pack of 100 per 100 m².
Nibbler
Power tool that cuts sheet metal cold, in small bites, without hot sparks. Recommended for cutting the panels.
lm (linear metre)
Total length, in metres, of a set of parts placed end to end.
λ (lambda)
Thermal conductivity of an insulant, in W/m.K. The lower it is, the better the insulant. Our polyurethane: 0.022.
R (thermal resistance)
Ability of an insulant to slow down heat, in m².K/W. The higher R is, the better. Example: Romane Canal 60/105 = R 3.64.
Uc (thermal transmittance)
Amount of heat passing through the complete panel, in W/m².K. The lower Uc is, the better.
Excl. VAT / incl. VAT
Excluding / including VAT. Our prices are shown excluding VAT by default; incl. VAT adds 20% French VAT.
No word matches. Ask us on +33 6 76 45 67 57 or write to us.