Installation guide
Install your sandwich-panel roof, step by step
Measure, check the roof frame, cut, install, finish. Each step comes with calculators to prepare your order, and a glossary for every technical word.
Before ordering: check the pitch and measure
Our panels can be installed from a 10% pitch, with no end overlap along the length. Check your , then measure the width and the of each roof slope.
Pitch calculatorHeight and length on the ground are enough
Formula: pitch (%) = height ÷ horizontal length × 100.
Panel and accessory calculatorIndicative quantities, to be confirmed by the quote
Available lengths: from 2.10 m to 12.25 m in 35 cm steps; from 12.60 m to 15.75 m as a special length (suitable transport required).
Get the exact price- The width along the gutter, from one gable to the other. One panel covers 1 m of effective width.
- The slope length, from the ridge to the gutter edge, following the slope. It is longer than the measurement on the ground.
- The overhang: add 20 to 40 cm at the eaves to keep water away from the walls.
- The panel length = slope length + overhang, rounded up to the next available length.
Check the roof frame
The panels are laid on made of timber or steel. The greater the , the lower the permissible load: in areas with heavy snow or strong wind, bring the purlins closer together. If in doubt about your roof frame, have it checked by a professional.
Load capacity by purlin spacingPermissible load in kg/m²
Delivery and storage
Delivery arrives on a 35-tonne curtain-sider, with the panels stacked on pallets. Prepare access and unloading before the day.
Access for a 35-tonne lorry
The address must allow an articulated lorry through. Otherwise, give us another unloading location.
Unloading is your responsibility
Plan for a forklift or a telehandler (Manitou). The calculator above estimates the weight to unload.
Store flat, raised off the ground
Somewhere dry, slightly tilted so that water runs off.
Handle with two people
By the edge, with two people for long lengths, without sliding the panels over each other.
Remove the protective film no later than 30 days after exposure to the sun
After that, it sticks to the panel. Ideally, remove it right after installation.
Cut without damaging the lacquer
Hot cutting burns the lacquer and makes the steel rust. The right tool makes all the difference.
Cut cold
- Electric shears
- Fine-toothed metal saw
Never use an abrasive tool
- Angle grinder, cut-off saw
- Their hot sparks attack the lacquer
- They cause rust over the whole surface
- Mark the cut with a grease pencil and support the panel on trestles.
- Cut slowly, wearing goggles, gloves and ear protection.
- Remove the swarf straight away with a soft cloth or brush: it rusts and stains.
- Treat cut edges and verges with an anti-corrosion product.
Installing the panels
Tick each step as the work progresses: your progress is saved on this device.
3D installation, step by step
Roof frame, screwing, interlocking, accessories: follow the assembly as on site.steps done
Installing the accessories
Tap a point on the house to see what each part is for and how to fix it.
Ridge cap
It covers the top of the roof. Three models depending on the shape:
- Ridge cap: two-slope roof, fitted astride the top.
- Wall abutment ridge: single-slope roof against a wall.
- Closure ridge: single-slope roof with a free top edge.
U-shaped verge trim
It finishes the side of the roof when the panel overhangs the gable. This is the most common verge trim, offered by default.
L-shaped verge trim
It is used when the panel stops flush with the wall, with no side overhang. On the diagram, it is shown on the other slope to compare the two profiles.
Eaves closure
Also called a front cover: it is the same part. Fixed at the end of each panel, at the eaves, it fills the gap under the wave and hides the insulating foam, against wind, rain and birds.
Finishing and maintenance
A few minutes on installation day, then a quick check once a year.
On installation day
- Remove the film and clean off all swarf.
- Touch up scratches with the touch-up paint in the panel colour.
Every year
- Visual check: screws, verge trims, ridge, cleanliness.
- Marine, corrosive or chemically aggressive environment: the standard polyester coating is not suitable, contact us before ordering.
General technical data sheet — Romane Canal, Flat Tile, Trapezoidal Steel
3-page PDF (in French): composition, performance, permissible loads, installation, accessories and delivery. The declaration of performance is sent on request at +33 6 76 45 67 57.
Roofing glossary
The technical words used in the guide and on the website, explained simply.
- Sandwich panel
- Panel made of two steel sheets and an insulating polyurethane foam core. In a single installation, it replaces the roofing, the insulation and the ceiling.
- 40/80, 60/105, 50/77 mm
- Insulation thickness of a wave-profile panel. The first figure is the thickness in the trough of the wave, the second at the highest point. Example: 40/80 = 40 mm in the trough, 80 mm at the crest.
- Effective width
- Width actually covered by a panel once interlocked with its neighbour: 1 m for our tile panels.
- Polyurethane (PUR)
- Insulating foam forming the core of the sandwich panel, between the two steel sheets.
- Protective film
- Plastic film that protects the lacquered face during transport. Remove after installation, no later than 30 days after exposure to the sun.
- Slope length
- Length of the roof measured along the slope, from the ridge to the gutter.
- Pitch
- Slope of the roof, expressed in % (height ÷ horizontal length × 100) or in degrees. Minimum for our panels: 10%.
- Overhang
- Part of the panel that projects beyond the wall, at the eaves (20 to 40 cm) or at the sides. It keeps rainwater away from the walls.
- Gable
- Wall whose top follows the triangular shape of the roof.
- Purlin
- Horizontal member of the roof frame (timber or steel) on which the panels rest and are screwed.
- Purlin spacing
- Distance between the centres of two purlins. Recommended maximum: 2 m.
- Load capacity
- Load (snow, wind, maintenance) the panel can bear, in kg/m², depending on purlin spacing.
- Ridge, ridge cap
- The ridge is the line at the top of the roof. The ridge cap is the metal part that covers it.
- Verge trim (U, L)
- Profile that finishes the sides of the roof (gables). The U-shaped trim is used when the panel overhangs the wall, the L-shaped trim when it stops flush with the wall.
- Eaves closure
- Part fixed at the end of each panel, at the eaves. It fills the gap under the wave and hides the insulating foam, against wind, rain and birds. Also called a front cover: it is the same part.
- Fixing screw
- Watertight screw with washer that fixes the panel to the purlins: 2 to 3 per panel per support, i.e. 2 to 4 per m² on average.
- Stitching screw
- Small screw that joins two neighbouring panels at their side lap. Allow 1 pack of 100 per 100 m².
- Nibbler
- Power tool that cuts sheet metal cold, in small bites, without hot sparks. Recommended for cutting the panels.
- lm (linear metre)
- Total length, in metres, of a set of parts placed end to end.
- λ (lambda)
- Thermal conductivity of an insulant, in W/m.K. The lower it is, the better the insulant. Our polyurethane: 0.022.
- R (thermal resistance)
- Ability of an insulant to slow down heat, in m².K/W. The higher R is, the better. Example: Romane Canal 60/105 = R 3.64.
- Uc (thermal transmittance)
- Amount of heat passing through the complete panel, in W/m².K. The lower Uc is, the better.
- Excl. VAT / incl. VAT
- Excluding / including VAT. Our prices are shown excluding VAT by default; incl. VAT adds 20% French VAT.